What is driving demand
AEMO's 2026 Integrated System Plan forecasts that the grid electricity used by business and industry will double, from 140 TWh in 2026 to 280 TWh in 2050. Data centres use about 2% of grid electricity today, and AEMO projects that they will use almost 10% of demand in the national electricity market by 2050. In NSW, data centres were seeking network connections totalling up to 28 GW in July 2026, while the state's average daily demand is 7.5 to 10 GW. Conventional industrial users need more power too, for automation, cold storage and electric fleets.
Where the network is full
Transgrid, which runs the NSW transmission network, said in August 2026 that Sydney's transmission network does not have the capacity today to connect any of the 20 GW of enquiries it has received for new large loads. In June it had assessed capacity in Western Sydney as largely exhausted beyond 2033.
A study for the Property Council expects the data centre pipeline to use up Endeavour Energy's substation capacity in the Mamre Road, Erskine Park and Aerotropolis Core precincts, so that later projects there may face further delays or costs. In Melbourne's west, the distributors Jemena and Powercor warned in August 2026 that data centres were seeking more power than the grid could accommodate.
What it does to land value
Cushman & Wakefield reports that data centres choose sites mainly for access to power rather than transport. In Sydney transactions since 2020, it found data centres paying 35% more per square metre than industrial buyers for raw zoned land, 42% more for zoned and serviced land, and 67% more for land that is also benched. In 2025, data centres accounted for 17% of industrial land take-up nationally, and 27% in Sydney and Melbourne.
Who pays for new capacity
Transgrid says that when large new users drive the need for new transmission, they will bear its cost, rather than existing electricity customers. In Queensland, when Powerlink builds a new line or substation for an industrial development, the company that asked for it pays for the easements, the construction and the operation.
Buyers need to control the land
Since 14 August 2026, when Transgrid allocates network capacity to a large load of 30 MW or more, such as a data centre, the allocation is provisional at first. It becomes final only if the proponent meets five criteria within three months of the agreement, and one of them is ownership, purchase, settlement, acquisition or lease of the site.
How to find out about a site
Every electricity distribution network must publish an annual planning report with capacity and load forecasts for its zone substations. Endeavour Energy, for example, publishes a network capacity map that can be searched by postcode, and it gives estimated available capacity. For a written answer about a particular site, a network will take a preliminary enquiry. Ausgrid aims to reply within 10 business days, charges a fee set by the regulator, and can say whether upgrades are likely and what the timeframes would be. AEMO reports that large data centre connections have so far taken about two years from application to energisation.
What this means for landowners: our view
- On industrial land, the spare capacity of the nearest substation now affects value alongside zoning and servicing, so two sites with the same zoning can be worth quite different amounts.
- The published maps are estimates. A preliminary enquiry gives a written answer for a particular site, which carries more weight in a negotiation than a map.
- A buyer that needs a large connection may have to show it controls the land within months of securing capacity, so the timing in a contract can matter as much as the price.
- Network upgrades are generally paid for by the party that triggers them, so a buyer planning a large connection will allow for that cost in what it offers.
How we approach it
We check the power position of each industrial site before we make an offer, starting with the published capacity of the nearest zone substation. If you are thinking about an approach, we are happy to explain what we would look at.
Sources
- AEMO, "2026 Integrated System Plan" (25 June 2026)
- NSW Department of Climate Change, Energy, the Environment and Water, "Reforming electricity network connection and cost recovery arrangements for data centres in NSW", consultation paper (August 2026)
- Solve Property Group for the Property Council of Australia, "NSW Industrial Land Study: Supply, Vacancy & Absorption", version 3.1 (9 August 2026)
- Transgrid, "New transmission capacity in Sydney to be funded by data centres" (26 August 2026)
- Transgrid, "Update on network capacity for new large-scale loads in Western Sydney" (17 June 2026)
- Bloomberg, via Energy Connects, "Australian Data Center Power Delay Exposes AI Bottleneck" (19 October 2026)
- Cushman & Wakefield, "The Industrial Land Shift" (August 2026)
- Powerlink Queensland, "2026 Transmission Annual Planning Report", chapter 5 (October 2026)
- Transgrid, "Network Capacity Allocation Policy: Load connections" (effective 14 August 2026)
- Essential Energy, "Distribution Annual Planning Report 2025" (22 December 2025)
- Endeavour Energy, "Our network capacity map" (read 17 November 2026)
- Ausgrid, "Help planning your connection" (read 17 November 2026)
This note is general information as at 17 November 2026. It is not advice, and it does not describe any particular site. Please get advice on your own land.